Complex valve automation projects rarely go exactly to plan. The real measure of a delivery partner is often what happens when the specification changes, the schedule tightens and the original approach is no longer viable.
That was the situation HSP Valves faced on a recent emergency shutdown valve (ESDV) project for a major Middle East customer.
The original delivery strategy involved completing smaller valve automation packages at HSP’s Dubai facility, while larger valve packages, up to 48 inches in size, would be integrated at the valve manufacturer’s facility in China with support from HSP engineers.
As the project developed, and quite common in large, critical, and challenging engineered automated valve packages, the team had to include some engineering changes from the client. With our in-house engineering team, we handled this easily by quickly updating the designs, re-drafting the drawings, and obtaining approval.
The bigger challenge, however, arose when the customer’s programme became increasingly time-critical and the delivery strategy changed. HSP was asked to complete additional integration and testing in Dubai, requiring the team to reorganise the programme around a much tighter schedule.